In-house crews. 2-year workmanship warranty.
Downtown Condo Kitchen and Washrooms, Vancouver
Project Information
Category:
Cabinets
Location:
Downtown Vancouver, BC
Duration:
5 days
Crew size:
2
Project Brief
Dark Wood Grain to Sage Green
We painted the kitchen cabinets and two washroom vanities in a downtown Vancouver condo, taking them from a dark wood-grain finish to sage green with Renner topcoat. Even a job like this still takes time, because the coats need proper dry and cure time in between. This one was about 53 crew hours over 5 days, with an in-house crew of 2. Every job starts with a written quote.
Proper dry and cure time still matters
Project Important Checklist
- Protect floors, counters, walls, appliances and fixtures
- Remove doors, drawers and vanities as needed
- Prep, prime and bond
- Spray Renner topcoat
- Reinstall the doors, drawers and existing hardware
- Cleanup
Completed By
Oriah Contracting
In-house crews.
Every job starts with a written quote.
Work Report
- About 53 crew hours
- 5 days including dry and cure time
- Existing hardware was reused
Project Stats
- About 2 gallons of Renner topcoat
- About 3 gallons of primer
Table of Contents